All of our perimeter fence screening has now been finished and we now have a back gate. Part of our outside work was included in the tender with Brilliant Homes as we really wanted the house and surrounds 95% complete. Apparently this was the first time that the builder had also included outside work and I’m gathering from the results it won’t be the last time. The boundary fence looks fantastic and so many people that have passed by have commented on how great it all now looks.
We walked through the house today testing most of the electricals from power points, light switches to data points and found that there were a couple of lights and data points that weren’t working. Unfortunately there is still a long list of others to test but these will have to wait until we move in.
We have put together a comprehensive list of issues and defects and these have been sent to the builder with the hope that they will be actioned prior to us moving in.
Brilliant Homes have told us that they are in the process of collecting all of the required certificates in order to provide us with an interim occupancy certificate and that we are days away from moving into our new house.
No comments:
Post a Comment