Well this week the roof tiles went on, with the gutters the week before. The skylights will be installed next week and then I’m assuming all of the external doors will be installed apart from the main entrance pivot door; which will get us to lock up. So this means we are still on track for completion this year. The next major steps are the internal walls – rough in and then gyprock with a targeted completion of the end of August. In the meantime we have been confirming the colour and material for our eaves, screens and decking and the colour of our garage door.