Since the last blog post we have met up with the
builder to walkthrough the progress so far and correct/make decisions for the
rest of the build. There is still so much to do, so we think it is unlikely
that we will be finished this year but the builder is still optimistic. The
internal plaster boarding is still progressing slowly with corners still to do,
the waterproofing though for the wet rooms has now been done with the screeding
due to start next week.
Architraves, skirting and all of the internal,
laundry and front doors are now onsite ready for installation. Electricians were
onsite making the cut outs for all of the cabling/power points.
Next week we have also lined up a meeting with
the landscaper to discuss what needs to be done to complete the build.
On the inside though we still need to confirm the internal robe layouts and
view another build site with the robes installed.