Saturday, 1 November 2014

Floors done

So this is what has been going on since my last post – The floorboards have been laid in all of the upstairs rooms. The Quickslide wardrobe doors have been installed for all of the built ins. The internal doors, door frames and skirting boards have also been done. The alfresco deck has been done and it is level with the inside floorboards so that we have a seamless inside/outside dining area – yipee!

The shed door has been made and installed using the same Ekowood material as the eaves and decking.


Monday, 27 October 2014

Drive by

I did a drive by and noticed that the front door and sidelight had now been installed. I’m not too sure if I like the opaque sidelight, I think I would have preferred clear glass, but this is something my partner wanted so I let this one slide. The Chippys were inside working on installing the floorboards and doors/architraves etc.



The tilers should be in next and then we’ll be on the home stretch. The viewing of the internal robes at another site has been delayed again as that home was having its floorboards polished so access was limited. Hopefully we will get to see them this Friday so that we can finalise that component.

Friday, 17 October 2014

Landscaping

We met with the landscaper and we already get the feeling that this will be an expensive exercise. We are keeping the plan simple with just continuing the existing hedging “Murraya” and “Photinia Robusta” around the perimeter of the site with a couple of feature trees here and there.

We have decided to not put in the planned external stairs instead we are creating a large planter to house a medium size blossom tree which I have wanted for some time now. The plan is also to have some flowering plum trees at the edge of the kitchen landing so that it is reflected in the kitchen splash back. I’m really hoping that this comes about as I imagined.

Friday, 10 October 2014

Another walkthrough

Since the last blog post we have met up with the builder to walkthrough the progress so far and correct/make decisions for the rest of the build. There is still so much to do, so we think it is unlikely that we will be finished this year but the builder is still optimistic. The internal plaster boarding is still progressing slowly with corners still to do, the waterproofing though for the wet rooms has now been done with the screeding due to start next week.

Architraves, skirting and all of the internal, laundry and front doors are now onsite ready for installation.  Electricians were onsite making the cut outs for all of the cabling/power points.
Next week we have also lined up a meeting with the landscaper to discuss what needs to be done to complete the build.

On the inside though we still need to confirm the internal robe layouts and view another build site with the robes installed.

Friday, 26 September 2014

Some progress

The outside courtyard is underway with excavation done in order to construct the planter box walls for the pre-existing hedges and new ones that will come with the landscaping.

The two sets of glass stacker doors are finally in plus the bi-folds that lead out to the seamless alfresco.


Also from what we can see most of the internal boarding has been done. So overall we are progressing slowly.

Saturday, 13 September 2014

Scaffolding has come down

So two weeks have passed and the eaves are now finished and the scaffolding has come down. There doesn’t appear to have been any changes to the internal, but we do know that the Gyprock and timber floorboards should be in very soon, maybe after the glass stacker and bifold doors are installed?

On the outside our brick façade around the garage is now complete including the electrical wiring, so now it just needs the Shale Grey acrylic render.




Saturday, 30 August 2014

Slat eaves are going on

The eaves have started to go on and boy do they look shmick! We decided to have all of our wood work in a composite wood (Eko wood supplied by Ekologix available at Bunnings) so as to reduce our maintenance bill. This material feels and looks like wood but it is a product of bamboo and recycled plastic.

No oiling or painting is required and it will not fade – good stuff!